data-dictionary

FPSADMIN.CAL_WORK_DAYS

Data Dictionary

>

FPSADMIN Tables

> FPSADMIN.CAL_WORK_DAYS

Table FPSADMIN.CAL_WORK_DAYS"

All known work days including past, present, and future.

  • Schema: FPSADMIN

  • Tablespace: FPSDATA

  • Primary key: START_WORK_DAY

  • Foreign keys: CAL_WORK_DAYS_FK_WEEK: START_WEEK REFERENCES FPSINPUT.CAL_WORK_WEEKS (START_WEEK)

  • Referenced by: FPSINPUT.CAL_SHIFTS (START_WORK_DAY)


Column

Type

Nullable

Comment

START_WORK_DAY

DATE

N

Work days must be 24 hours in length and the start of the work day must be the start of one of the shifts. Contrast this to plan day which is independent of shift.

CALENDAR_DAY

DATE

N

When we choose this day on a website calendar we will associate with work_days of this day. Typically this is the day of the start_day but not always. For example, start_day might be 17:00 and represent the following calendar_day.

DAY_OF_WEEK

VARCHAR2(3)

N

This should be Mon, Tue, etc.

END_WORK_DAY

DATE

N

It is critical that this field equal the start_work_day of the next work day.

START_WEEK

DATE

N

Work weeks must be 7 days in duration and the start of the work week must be the start of one of the work days. (* from FPSINPUT.CAL_WORK_WEEKS)