Queue timers can start at either DISPATCH, BEGIN, END, or COMP of the start step. END is preferred and is the default. The timer always ends with the BEGIN at the end step. This logic first calculates when the timer started (queue_start_inst) and then filters for lots where indeed the timer has started as well as not yet ended. These are the lots which we consider to be in a queue timer meaning: 1) We will consider increasing the priority to avoid missing the queue timer in RTG_QUEUE_MULTI_AREA_PRTY. This view includes some logic for this which is described in comments of that view. 2) We assume these lots will run ahead of any lot which we are considering whether to start into a new timer in RTG_QUEUE_MULTI_AREA_START.

Column

Comment

LOT

A lot is a group of units that process together. Usually lot_id or lot_number in MES. All units in a lot are in the same carrier but there may be multiple lots in a carrier. (* inherited from FPSINPUT.WIP_LOTS_STATIC)

TIMER_ID

Unique number representing the queue timer to index with other tables. Automatically populated with RTG_QUEUE_TIMERS_ID_SEQ sequence. (* inherited from FPSINPUT.RTG_QUEUE_TIMERS)

CURR_QTY

Current qty of the lot using quantity unit of the current facility. (* inherited from FPSBASE.WIP_FLUSH)

NUM_STEPS_AWAY

Number of steps away not including steps which we know will be skipped nor those which we estimate will be skipped at least x pct of the time. This x value is configurable in GEN_FACILITIES using the smp_pct_for_num_steps_away column. (* inherited from FPSBASE.WIP_STEP_FUTURE)

PROCESS_FAMILY

See https://help.inficonims.com/display/DW/Guide+to+Process+Families. (* inherited from FPSINPUT.RTG_PROCESS_FAMILIES)

PROCESS_SUBFAMILY

Route step family is used for the Dashboard to separate processes in a process family based on shared but limited assignments. It is also the base for GP subfamily. (* inherited from FPSBASE.RTG_ROUTE_STEPS_PLUS)

END_STEPS_AWAY

QUEUE_START_INST

XFACTOR_RQD

EXPIRED_SEC

Seconds from the start event until queue time restriction is expired. After expiration, the lot must rework or scrap or otherwise be evaluated. (* inherited from FPSINPUT.RTG_QUEUE_TIMERS)

EXPIRED_INST

EXPIRED_INST_PLUS_TCT

END_STEP_COMP_INST_IF_TCT

RWK_IF_EXPIRED

Indicates whether rework is required after queue timer expires. If allowed, we need to specify the route and step that we expect the lot to move into for rework. (* inherited from FPSINPUT.RTG_QUEUE_TIMERS)

CURR_STEP_ENT_INST

PROCESS

Process defines what occurs at a step. Different steps can share the same process if they are identical. Process should normally determine allowed tools and recipe although it can be overridden by step, route, prd, lot, and experiment for exceptions. Each process is dynamically assigned to one or more eqp_type-process_family combinations with use_pct. One process_family is determined to be primary. If grouping is done correctly, a process should only be one eqp_group with no crossover. (* inherited from FPSINPUT.RTG_PROCESSES)

EST_MACHINE_RECIPE

Estimated machine recipe what we estimate will be the machine recipe based on information from the Recipe Management System. It is used in combination with process for throughput calculations and setup change penalty calculations. It is not necessary to estimate for all processes since this is always used in combination however it needs to be NA rather than blank since it is part of the primary key of most THP tables. Hopefully when this is not NA it should match the actual machine recipe logged for each lot during processing. (* inherited from FPSINPUT.RTG_TOOL_ASSIGNMENTS)

SCHED_TOOL

the tool from the first lot that scheduled (* inherited from FPSAPP.SCH_W_SCHED_DURABLE_INSPECT)

SCHED_CH_TO_USE

Please note that the Scheduler often populates this with M which indicates the main tool therefore we often should filter out a value of M when using this value since that it not a valid chamber combination. When this is populated with any value other than M then we use this as est_ch_used rather than calculating with GET_CH_ALLOWED_STATUS or GET_CH_PATH_STATUS. (* inherited from FPSBASE.WIP_STEP_FUTURE_SCHED)

SCHED_START

The first start time for the durable to be used (* inherited from FPSBASE.RTG_DURABLE_FUTURE_SCHED)

SCHED_QTY_IN_JOB

FACILITY

Facility is included in almost every join in the DWH so this represents a definitive split. A route must have all steps on tools in the same facility. A tool must process all lots in the same facility. If your site has multiple buildings where lots run on routes using tools in multiple buildings then everything should be one facility. For example, multiple Fab buildings. But if your site has independent facilities like Fab and Test and Assembly where lot may progress from one to the next but on different routes then these should be different facilities. Since this column is in virtually every table it is critical that the value here is exactly matches what is in the MES if the MES has facility. Use facility_display for the display friendly name displayed in applications. See site_name comment for client/site/facility example. (* inherited from FPSINPUT.GEN_FACILITIES)

START_STEP

Start step that will impact the future thread step rank in RTG_TOOL_ASSIGNMENT_LOT (* inherited from FPSINPUT.RTG_STEP_THREADING)

CURR_STEP

END_STEP

The step upon move out where the WIP balance limit is no longer applied (* inherited from FPSINPUT.RTG_STEP_BALANCE)

ROUTE_OF_END_STEP

EST_SMP_PCT

Smp_pct tells you what percentage of the lots complete on a tool. Some sites skip steps by jumping over them so we see the lot move from step 3 to step 5 and we only know that it jumped step 4 because step 4 is on the route between 3 and 5. Other sites skip steps by moving lots into them and then moving them out a second later so we see a move from 3 to 4 at 11:11:11 and a move from 4 to 5 at 11:11:12. We do not care how it is done but just that the lot did not process at step 4 -- and to be more specific that no tool capacity is required to process this lot at step 4 and no cycle time is accumulated at step 4. (* inherited from FPSBASE.WIP_GOAL_LOT_SHIFT)

IS_STAGING_STEP

We expect large amounts of WIP and long cycle times at staging steps. We still calculate cycle time like any other step but the important difference is that lots currently at a staging step are not counted as normal coming lots to future steps. Instead we show them in a special column labeled From Staging. (* inherited from FPSINPUT.RTG_ROUTE_STEPS)

ALWAYS_ALLOW_Q_WHEN_DOWN

Normally we do not allow lots to start at the first step in a queue timer sequence if there is a step in the sequence that has no tools available. But if this flag is set to Y then we will allow lots to start even when all tools are down at this process. Typically this is used for a process that we know we can skip but the est_smp_pct might be above the smp_pct_to_allow_q_when_down threshold set for the facility in GEN_FACILITIES. (* inherited from FPSINPUT.RTG_PROCESSES)