FPSBASE.WIP_DEMAND_BY_WEEK

Data Dictionary

>

FPSBASE Views

> FPSBASE.WIP_WAFER_HIST_LOOP

View FPSBASE.WIP_DEMAND_BY_WEEK

This view summarizes our demand by plan week for use in WIP_FLUSH. The key feature of this view is that is subtracts what has already shipped from the current week demand.

Column

Comment

FACILITY

Facility is included in almost every join in the DWH so this represents a definitive split. A route must have all steps on tools in the same facility. A tool must process all lots in the same facility. If your site has multiple buildings where lots run on routes using tools in multiple buildings then everything should be one facility. For example, multiple Fab buildings. But if your site has independent facilities like Fab and Test and Assembly where lot may progress from one to the next but on different routes then these should be different facilities. Since this column is in virtually every table it is critical that the value here is exactly matches what is in the MES if the MES has facility. Use facility_display for the display friendly name displayed in applications. See site_name comment for client/site/facility example. (* inherited from FPSINPUT.GEN_FACILITIES)

PLANPRD

Planning product used for all planning purposes. All lots with the same planprd are interchangeable to ship to the customer regardless of their prd, route, technology, wafer size, etc. For detailed information on prd vs. planprd see table comments in RTG_PLANPRDS. (* inherited from FPSINPUT.RTG_PLANPRDS)

LOT_GROUP

Lot_group is a grouping of lot_family and is the highest grouping in the lot type hierarchy. There should be only a few values for lot_group, i.e. Prod, Dev, TW. We group WIP and moves by lot_group on the dashboard and we group cycle time calculations by lot_group so this is an important field. (* inherited from FPSINPUT.WIP_LOT_GROUPS)

START_PLAN_WEEK

Plan weeks must be 7 days in duration and the start of the plan week must be the start of one of the plan days. (* inherited from FPSINPUT.CAL_PLAN_WEEKS)

END_PLAN_WEEK

It is critical that this field equal the start_plan_week of the next plan week. (* inherited from FPSINPUT.CAL_PLAN_WEEKS)

PLAN_WEEK

Name of plan week must be unique and can be in any format as long as it is display friendly since this is what we show everywhere. (* inherited from FPSINPUT.CAL_PLAN_WEEKS)

DEMAND_QTY_WEEK

SHIP_QTY_THIS_WEEK

CUM_DEMAND_INCL_THIS_WEEK

CUM_DEMAND

REM_DEMAND_QTY_WEEK